Cost · 6 min read

What it really costs to open a hospital in India

Beds, building and what is inside: how a hospital budget is built, using four published reference models from a polyclinic to 100 beds.

Ask what a hospital costs and you will usually hear “it depends”. It does, on three things: how many beds, what goes inside, and the building you start with. Here is how the numbers work, using the four reference models we publish.

Four benchmarks

ModelAreaBedsStarting priceShell to opening
Polyclinic600 sq ft2₹15–25 lakh2–3 months
25-bed hospital5,500–6,000 sq ft25₹1.26 crore4–6 months
50-bed hospital10,000–12,000 sq ft50₹2.5 crore6–9 months
100-bed hospital20,000–25,000 sq ft100₹6 crore9–12 months

These are starting prices for a turnkey fit-out of a ready building. Each model and its full inclusion list is on the Launch & Scale page.

What the price includes

  • Planning: layout, department flow and the itemised inclusion list
  • Interiors and fit-out of every department
  • Medical equipment and hospital furniture, installed and commissioned
  • Oxygen lines, power backup and biomedical waste arrangements
  • Licensing support, run alongside the fit-out
  • Recruitment of the team you need on opening day

What it does not include

  • Land. Every plot is different, so it is never part of a package.
  • The civil shell. If you are building from bare land, the structure is planned and priced separately for your site.
  • Working capital. Salaries, consumables and running costs for the months before the hospital breaks even.

What moves the number

Critical-care beds

An ICU, HDU or NICU bed carries monitors, ventilator support, medical gas outlets and more nursing. A hospital with a larger critical-care block costs more than one with the same bed count in wards.

Imaging

X-ray and ultrasound are part of most models. Adding a CT scanner changes the budget, the room design and the licensing.

Operation theatres

The number of theatres, and whether they are modular, is one of the largest single decisions in the budget.

The building you start with

Fitting out an existing building is faster and cheaper than building from the ground up, but the building has to suit a hospital: floor loads, ceiling heights, ramps and lift space. We check this before you commit.

The package price is a starting point. It moves only when you change the inclusions, and you see the itemised list before you commit a rupee.